Tax Management India. Com
Law and Practice  :  Digital eBook
Research is most exciting & rewarding
  TMI - Tax Management India. Com
Follow us:
  Facebook   Twitter   Linkedin   Telegram

Home Case Index All Cases Central Excise Central Excise + AT Central Excise - 2023 (10) TMI AT This

  • Login
  • Cases Cited
  • Referred In
  • Summary

Forgot password       New User/ Regiser

⇒ Register to get Live Demo



 

2023 (10) TMI 873 - AT - Central Excise


Issues Involved:
1. Whether the activity of packing, repacking, and relabelling of spare parts constitutes 'manufacture' under Section 2(f)(iii) of the Central Excise Act, 1944.
2. Applicability of the extended period of limitation for demanding duty.
3. Imposition of penalties on the appellants.

Summary:

Issue 1: Definition of 'Manufacture'
The appellant, a Public Sector Undertaking, engaged in the manufacture of Dump Trucks, Water Sprinklers, and Motor Graders, was also involved in repacking and relabelling spare parts. The dispute was whether these activities constituted 'manufacture' under Section 2(f)(iii) of the Central Excise Act, 1944. The Tribunal divided the period into two phases: January 2008 to February 2010, and March 2010 to March 2011. For the first period, it was determined that the parts involved were not 'automobiles' as per the Larger Bench decision in M/s. Action Construction Equipment Ltd., thus falling outside the scope of Sl. No.100 of the Third Schedule. Therefore, these activities did not amount to 'manufacture' and were not leviable to excise duty. However, for the second period, the amended entry at Sl. No.100 of the Third Schedule covered these activities under 'deemed manufacture'.

Issue 2: Extended Period of Limitation
The appellant argued that the extended period of limitation could not be invoked based on the Tribunal's decision in their own case, M/s. BEML & Ors. vs. CCE, where it was held that extended period could not apply for recovery of duty on the basis of retrospective legislation. The Tribunal agreed, noting that the appellant's activities commenced in 2006, and the retrospective amendment was only applicable from March 2010. Thus, invoking the extended period of limitation was deemed unsustainable, confining the demand to the normal period of limitation.

Issue 3: Imposition of Penalties
Given the findings on the non-applicability of the extended period of limitation and the nature of the activities not amounting to 'manufacture' for the first period, the Tribunal found the imposition of penalties on the appellants unwarranted. Consequently, all penalties imposed were set aside.

Conclusion:
The appeal was partly allowed, limiting the demand to the normal period of limitation and setting aside all penalties imposed on the appellants.

 

 

 

 

Quick Updates:Latest Updates