Tax Management India. Com
Law and Practice  :  Digital eBook
Research is most exciting & rewarding
  TMI - Tax Management India. Com
Follow us:
  Facebook   Twitter   Linkedin   Telegram

Home Case Index All Cases Customs Customs + HC Customs - 2023 (11) TMI HC This

  • Login
  • Cases Cited
  • Summary

Forgot password       New User/ Regiser

⇒ Register to get Live Demo



 

2023 (11) TMI 493 - HC - Customs


Issues Involved:
1. Recovery of 2% Basic Customs Duty (BCD)
2. Deduction of excess quantity supplied at Chandrapur TPS
3. Liquidated damages on account of alleged short supply to Khaparkheda TPS
4. Short payment under Contract No. 2041
5. Limitation

Summary:

Issue 1: Recovery of 2% Basic Customs Duty (BCD)
The Petitioner argued that the Arbitral Tribunal erroneously dismissed the reliance on the Circular dated 21.10.2013, which clarified that the BCD was 0% and CVD was 2%. The Tribunal interpreted Clause 5.2 of the contract, determining it applied only to BCD and not CVD. The Tribunal found that the contract's price schedule correctly included 2% BCD and 2% CVD, making a total duty of 4%. The Circular was deemed clarificatory and irrelevant to the contract's terms. The Court upheld the Tribunal's interpretation, stating it was a possible view and thus not subject to interference under Section 34 of the Arbitration and Conciliation Act, 1996.

Issue 2: Deduction of Excess Quantity Supplied at Chandrapur TPS
The Petitioner contended that the Respondent supplied excess coal beyond the contractual quantity, considering a tolerance of +/- 2%. The Tribunal interpreted Clauses 8.7 and 8.11, concluding that the tolerance limit applied to the total contracted quantity, not independently to the diverted quantity. The Court found the Tribunal's interpretation was reasonable and upheld it, emphasizing it was not for the Court to re-interpret the contract.

Issue 3: Liquidated Damages on Account of Alleged Short Supply to Khaparkheda TPS
The Tribunal found no shortfall in the supply of coal beyond permissible limits, making the deduction of liquidated damages by the Petitioner impermissible. The Tribunal noted that the Petitioner failed to prove any damages suffered due to the alleged short supply. The Court agreed, stating that proving loss is a sine qua non for the applicability of Section 74 of the Contract Act, and without such proof, the deduction was unjustified.

Issue 4: Short Payment Under Contract No. 2041
The Tribunal found that reconciliation proceedings were not concluded, and the disputed amount was yet to be identified. The Petitioner denied owing Rs. 21,76,555/- under the Bhusawal Contract. The Court did not find any error in the Tribunal's findings on this issue.

Issue 5: Limitation
The Petitioner argued that the arbitration notice dated 31.08.2017 was barred by limitation, as the cause of action arose on 19.03.2014. The Tribunal found that part payments were made between October and November 2015, and joint reconciliation of accounts was completed in 2017. Thus, the claims were within limitation. The Court upheld this finding, noting that a Court under Section 34 cannot re-appreciate evidence.

Conclusion:
The Court dismissed the Arbitration Petition, finding no merit in the challenges raised against the Arbitral Tribunal's award. The Tribunal's interpretations and findings were deemed reasonable and not subject to interference under Section 34 of the Arbitration and Conciliation Act, 1996.

 

 

 

 

Quick Updates:Latest Updates