Tax Management India. Com
Law and Practice  :  Digital eBook
Research is most exciting & rewarding
  TMI - Tax Management India. Com
Follow us:
  Facebook   Twitter   Linkedin   Telegram

Home Case Index All Cases IBC IBC + AT IBC - 2025 (1) TMI AT This

  • Login
  • Summary

Forgot password       New User/ Regiser

⇒ Register to get Live Demo



 

2025 (1) TMI 1214 - AT - IBC


ISSUES PRESENTED and CONSIDERED

The core issues considered in this judgment include:

  • Whether the exclusion of the period from 12.04.2023 to 01.07.2024 from the implementation timeline of the Resolution Plan was justified.
  • Whether the interim order dated 12.04.2023, which restrained the Successful Resolution Applicant (SRA) from transferring any units, impacted the implementation of the Resolution Plan.
  • Whether the SRA took substantial steps towards implementing the Resolution Plan during the interim order period.
  • Whether the affidavit filed by Salil Barar, the then President of the SRA, was valid and should be considered.
  • Whether the objections raised by the appellants regarding the eligibility and actions of the SRA were relevant to the exclusion of time granted by the Adjudicating Authority.

ISSUE-WISE DETAILED ANALYSIS

1. Exclusion of Time from Implementation Timeline

  • Relevant Legal Framework and Precedents: The Tribunal considered the provisions of the Insolvency and Bankruptcy Code, 2016, and the guidelines regarding the implementation of Resolution Plans within stipulated timelines.
  • Court's Interpretation and Reasoning: The Tribunal noted that the interim order dated 12.04.2023 prevented the SRA from transferring units, which was a significant source of funding as per the Resolution Plan. This restriction justified the exclusion of the period from the implementation timeline.
  • Key Evidence and Findings: The SRA had proposed to generate Rs.50 crores from the sale of unsold inventory, which was hindered by the interim order. The Tribunal found that the inability to realize this amount due to the interim order significantly impacted the implementation of the Resolution Plan.
  • Application of Law to Facts: The Tribunal applied the principles of equity and fairness, considering that the interim order was beyond the control of the SRA and directly affected the execution of the Plan.
  • Treatment of Competing Arguments: The appellants argued that the interim order did not prevent the SRA from implementing the Plan. However, the Tribunal found that the restriction on transferring units directly impacted the SRA's ability to secure necessary funds.
  • Conclusions: The Tribunal upheld the Adjudicating Authority's decision to exclude the period from the implementation timeline, recognizing the genuine impediments faced by the SRA.

2. Actions Taken by SRA During Interim Order Period

  • Relevant Legal Framework and Precedents: The Tribunal examined the obligations of the SRA under the approved Resolution Plan.
  • Court's Interpretation and Reasoning: The Tribunal found that the SRA had taken substantial steps towards implementing the Resolution Plan, including securing necessary licenses and clearances, despite the interim order.
  • Key Evidence and Findings: The SRA had spent significant amounts on various aspects of the project, including structural repairs, environmental clearances, and utility connections. The Tribunal considered these actions as evidence of the SRA's commitment to the Plan.
  • Application of Law to Facts: The Tribunal applied the principle that actions taken in good faith towards fulfilling contractual obligations should be recognized, even if full compliance was hindered by external factors.
  • Treatment of Competing Arguments: The appellants contended that the SRA had not fulfilled its financial obligations. The Tribunal noted that the SRA had infused Rs.7 crores and had made substantial progress in other areas, which justified the exclusion of time.
  • Conclusions: The Tribunal concluded that the SRA had acted diligently and in good faith, warranting the exclusion of the period from the implementation timeline.

3. Validity of Affidavit Filed by Salil Barar

  • Relevant Legal Framework and Precedents: The Tribunal considered the procedural validity of affidavits in legal proceedings.
  • Court's Interpretation and Reasoning: The Tribunal found that the affidavit filed by Salil Barar was valid and relevant, as it provided crucial information regarding the actions taken by the SRA.
  • Key Evidence and Findings: The Tribunal noted that Salil Barar was the President of the SRA at the time of the Resolution Plan approval and had the authority to file the affidavit.
  • Application of Law to Facts: The Tribunal applied the principle that affidavits must be considered if they provide material information relevant to the case.
  • Treatment of Competing Arguments: The appellants challenged the authority of Salil Barar to file the affidavit. The Tribunal dismissed this challenge, noting the ongoing legal proceedings regarding the appointment of an Administrator.
  • Conclusions: The Tribunal accepted the affidavit as valid and relevant to the case.

SIGNIFICANT HOLDINGS

  • Preserve verbatim quotes of crucial legal reasoning: The Tribunal emphasized, "The interim order passed by this Tribunal clearly prohibited the SRA to realize the aforesaid amount of Rs.50 crores."
  • Core Principles Established: The Tribunal established that interim orders affecting the financial execution of a Resolution Plan justify the exclusion of time from the implementation timeline.
  • Final Determinations on Each Issue: The Tribunal dismissed the appeals, affirming the Adjudicating Authority's decision to exclude the period from 12.04.2023 to 01.07.2024 from the implementation timeline of the Resolution Plan.

 

 

 

 

Quick Updates:Latest Updates