Tax Management India. Com
Law and Practice  :  Digital eBook
Research is most exciting & rewarding
  TMI - Tax Management India. Com
Follow us:
  Facebook   Twitter   Linkedin   Telegram

Home Case Index All Cases Income Tax Income Tax + AT Income Tax - 2020 (9) TMI AT This

  • Login
  • Cases Cited
  • Summary

Forgot password       New User/ Regiser

⇒ Register to get Live Demo



 

2020 (9) TMI 611 - AT - Income Tax


Issues Involved:
1. Whether the deduction under section 80-IB(10) of the Income Tax Act, 1961, can be allowed if the housing project was not completed within the specified period of four years from the date of commencement.
2. Whether the deduction under section 80-IB(10)(f) was correctly allowed.

Issue-wise Detailed Analysis:

1. Deduction under Section 80-IB(10) and Completion Period:

The primary issue was whether the assessee was entitled to a deduction under section 80-IB(10) despite the completion certificate for the housing project not being issued within four years from the commencement date. The assessee, engaged in the business of promoters, builders, and land developers, filed returns declaring a total income of ?21,37,560/- after claiming a deduction of ?1,98,14,321/- under section 80-IB(10) for a housing project. The Assessing Officer (AO) disallowed the deduction, citing that the completion certificate for buildings A, B, and C was not issued by the local authority by 31st March 2012, the stipulated date.

The assessee argued that all flats in buildings A, B, and C were sold, and possession was handed over before the due date. The necessary NOCs were obtained, and an application for the completion certificate was submitted on 14th March 2012. The assessee contended that the delay in issuing the completion certificate by the local authority should not invalidate the deduction claim, supported by judicial precedents indicating that the formal issue of the completion certificate was not mandatory if substantial evidence showed the project was completed on time.

The Commissioner of Income Tax (Appeals) [CIT(A)] accepted the assessee's arguments, noting that the project was indeed completed on time, supported by an architect's certificate, sale deeds, possession receipts, and utility bills. The CIT(A) referred to several judgments, including the Supreme Court's decision in Bajaj Tempo Ltd., which emphasized a liberal interpretation of incentive provisions like section 80-IB.

The Tribunal upheld the CIT(A)'s decision, agreeing that the requirement for a formal completion certificate from the local authority was not mandatory if substantial compliance with section 80-IB(10) was demonstrated. The Tribunal cited cases like CIT vs. Tarnetar Corporation and Siddhivinayak Kohinoor Venture vs. ACIT, where similar claims were allowed based on substantial evidence of project completion and timely application for the completion certificate.

2. Deduction under Section 80-IB(10)(f):

The second issue involved the correctness of allowing the deduction under section 80-IB(10)(f). The AO had disallowed the deduction, partly based on the revision of the project plan in 2014, which he claimed violated section 80-IB(10)(f). However, the CIT(A) found that buildings A, B, and C were completed before the due date, supported by the architect's certificate and other evidence.

The Tribunal, after reviewing the submissions and evidence, concluded that the assessee had substantially complied with the requirements of section 80-IB(10). The Tribunal noted that the delay in issuing the completion certificate was not attributable to the assessee and that the project was completed within the stipulated period based on the evidence provided. Therefore, the deduction under section 80-IB(10)(f) was correctly allowed.

Conclusion:

The Tribunal dismissed the Revenue's appeal, upholding the CIT(A)'s decision to allow the deduction under section 80-IB(10) for the assessee's housing project. The Tribunal emphasized that substantial compliance with the section's requirements, supported by adequate evidence, was sufficient for claiming the deduction, even if the formal completion certificate was delayed by the local authority. The appeal was dismissed, and the order was pronounced on 9th September 2020.

 

 

 

 

Quick Updates:Latest Updates