installation certificate, Central Excise |
||||
|
||||
installation certificate |
||||
sir,
We had imporing machinery from china under 0% EPCG scheme , now we want to take installation certi from excise department because we are registred with excise dept . Now question is that inspector and supt also not ready to received our request letter of INSTALLATION CERTI ( atteched all EPCG related documens ) . He insest that please submit Charted engg certificate , without this we can't received your letter . As per my knoledge & also we have taken installation certi about 50 nos. M/c with out Charted engg ceti and as per rules there is no need . What to do about this situation , we also give rule printout but he suggest that please submit Charted engg certi . Advance thanks . SACHIN
Posts / Replies Showing Replies 1 to 2 of 2 Records Page: 1
Though it is clear that no where it is mentioned that you have to obtain the CE Certificate before getting the Installation Certificate from Excise except in case of Spares, most of the officer ensist on CE certificate as a evidence of third party confirmation. It is advisable to arrange the CE certificate instead of going into argument.
good evening Mr. sachin,
You can go through the CBEC circular No., 14/2008-Cus dated 26.9.2008 and submit a copy of the same to the department This should help you out of the present situation.
But obtaining Chartered engineer's certificate would hlep you to get the installation certificate from the department
With best wishes
Rangaswamy Page: 1 Old Query - New Comments are closed. |
||||