Tax Management India. Com
Law and Practice  :  Digital eBook
Research is most exciting & rewarding
  TMI - Tax Management India. Com
Follow us:
  Facebook   Twitter   Linkedin   Telegram

Home Case Index All Cases Indian Laws Indian Laws + HC Indian Laws - 2019 (2) TMI HC This

  • Login
  • Cases Cited
  • Referred In
  • Summary

Forgot password       New User/ Regiser

⇒ Register to get Live Demo



 

2019 (2) TMI 2027 - HC - Indian Laws


Issues Involved:
1. Whether the claims made by the petitioner (NCCL) are "Notified Claims" under the terms of the contract.
2. The jurisdiction of the General Manager to determine the arbitrability of the claims.
3. The impact of the "No Claim Certificate" and subsequent withdrawal of claims by NCCL.
4. The applicability of Section 11(6A) of the Arbitration and Conciliation Act, 1996, and its effect on the court’s role in appointing an arbitrator.
5. Whether the disputes should be referred to arbitration despite the General Manager's decision.

Detailed Analysis:

1. Notified Claims:
The petitioner, NCCL, sought arbitration for claims arising from a delayed project. IOCL resisted, arguing that the claims were not "Notified Claims" as per the contract, which required claims to be notified within ten days of the event causing the claim. The court examined the relevant clauses of the General Conditions of Contract (GCC), particularly Clause 1.21.0.0 defining "Notified Claims" and Clause 6.6.1.0 detailing the notification requirements. The court noted that NCCL had provided the necessary notices and included the claims in the final bill, thus fulfilling the conditions for "Notified Claims."

2. General Manager's Jurisdiction:
IOCL argued that its General Manager had the final authority to determine whether claims were "Notified Claims" and thus arbitrable. The court analyzed Clause 9.0.2.0, which grants the General Manager the power to decide on the arbitrability of claims. However, the court found that the clause did not explicitly state that the General Manager's decision was final. The court emphasized that allowing one party unilaterally to determine arbitrability could undermine the arbitration process and the statutory power conferred on the Arbitral Tribunal under Section 16 of the 1996 Act.

3. No Claim Certificate:
NCCL had issued a "No Claim Certificate" under duress, as IOCL had indicated that the final bill and EOT requests would only be processed if NCCL withdrew its claims. The court found that this constituted coercion, making the certificate invalid. The court referenced the Supreme Court's decision in National Insurance Co. Ltd. v. Boghara Polyfab (P) Ltd., which held that issues of coercion or duress should be examined by the Arbitral Tribunal.

4. Section 11(6A) of the Arbitration and Conciliation Act, 1996:
The court highlighted the limited scope of judicial intervention under Section 11(6A), which confines the court's role to ascertaining the existence of an arbitration agreement. The court cited the Supreme Court's judgment in Duro Felguera S.A. v. Gangavaram Port Limited, emphasizing that the court should only ensure that an arbitration agreement exists and should leave questions of arbitrability to the Arbitral Tribunal.

5. Referral to Arbitration:
The court concluded that the disputes should be referred to arbitration. It appointed Hon’ble Mr. Justice Madan B. Lokur as the arbitrator, noting that the General Manager's decision did not preclude arbitration. The court emphasized that any contestation regarding the claims being "Notified Claims" or issues of coercion related to the "No Claim Certificate" should be decided by the Arbitral Tribunal.

Conclusion:
The court directed the appointment of an arbitrator to resolve the disputes between NCCL and IOCL, emphasizing the limited role of the court under Section 11(6A) and the necessity for the Arbitral Tribunal to determine issues of arbitrability and coercion. The decision underscores the importance of adhering to the arbitration agreement and the statutory framework governing arbitration in India.

 

 

 

 

Quick Updates:Latest Updates