Tax Management India. Com
Law and Practice  :  Digital eBook
Research is most exciting & rewarding
  TMI - Tax Management India. Com
Follow us:
  Facebook   Twitter   Linkedin   Telegram

Home Case Index All Cases Indian Laws Indian Laws + HC Indian Laws - 2021 (4) TMI HC This

  • Login
  • Cases Cited
  • Referred In
  • Summary

Forgot password       New User/ Regiser

⇒ Register to get Live Demo



 

2021 (4) TMI 1356 - HC - Indian Laws


Issues Involved:
1. Existence and validity of the Arbitration Agreement.
2. Alleged economic duress and coercion in the execution of the Settlement Agreement.
3. Compliance with pre-arbitral steps as per the dispute resolution mechanism in the Contract Agreement.

Detailed Analysis:

Issue 1: Existence and Validity of the Arbitration Agreement
The principal controversy revolves around whether the Settlement Agreement novated the Contract Agreement, thereby extinguishing the Arbitration Clause contained within it. NTPC contended that the Settlement Agreement superseded the Contract Agreement, rendering the Arbitration Clause void. Conversely, SPML argued that the Settlement Agreement was invalid due to economic coercion and undue influence, thus the Arbitration Clause in the Contract Agreement remained effective. The Court noted that the Arbitration Clause is a collateral term of the contract and remains operative unless the contract is legally non-existent. The Court emphasized that the question of novation and the validity of the Settlement Agreement should be determined by the Arbitral Tribunal.

Issue 2: Alleged Economic Duress and Coercion
SPML claimed that it was compelled to sign the Settlement Agreement under economic duress as NTPC withheld the release of Bank Guarantees despite the project's completion. The Court acknowledged that SPML had repeatedly requested the release of the Bank Guarantees and had indicated financial constraints due to their non-release. The Court found that the dispute regarding whether the Settlement Agreement was executed under duress was not frivolous or insubstantial and thus should be examined by the Arbitral Tribunal. The Court referred to precedents indicating that issues related to economic duress and coercion should be determined in arbitration rather than at the pre-referral stage.

Issue 3: Compliance with Pre-Arbitral Steps
NTPC argued that SPML had not exhausted the mandatory pre-arbitral steps as per the dispute resolution mechanism in the Contract Agreement, which required mutual consultation and reference to an adjudicator before arbitration. SPML had sent a letter demanding payment and requested the appointment of an adjudicator, which NTPC did not fulfill. The Court concluded that SPML had made sufficient attempts to resolve the disputes amicably and had invoked the arbitration clause after NTPC's failure to appoint an adjudicator. Consequently, the Court found that the petition was not premature and that SPML had complied with the pre-arbitral steps.

Conclusion:
The Court allowed the petition, appointing Justice Manmohan Singh as NTPC's nominated Arbitrator and directed both Arbitrators to jointly appoint the Presiding Arbitrator. The Court emphasized that the disputes regarding the validity of the Settlement Agreement and compliance with pre-arbitral steps should be resolved by the Arbitral Tribunal. The petition was disposed of in these terms.

 

 

 

 

Quick Updates:Latest Updates