Tax Management India. Com
Law and Practice  :  Digital eBook
Research is most exciting & rewarding
  TMI - Tax Management India. Com
Follow us:
  Facebook   Twitter   Linkedin   Telegram

Home Case Index All Cases Indian Laws Indian Laws + SC Indian Laws - 2018 (4) TMI SC This

  • Login
  • Cases Cited
  • Referred In
  • Summary

Forgot password       New User/ Regiser

⇒ Register to get Live Demo



 

2018 (4) TMI 851 - SC - Indian Laws


Issues Involved:
1. Invitation for refurbishment proposals and issuance of provisional Letter of Intent.
2. Furnishing of Bank Guarantees and Performance Bond.
3. Determination of Zero Date and subsequent correspondence.
4. Invocation of Bank Guarantees and issuance of notice for default.
5. Arbitration and Tribunal's award.
6. Section 34 application and Additional District Judge's findings.
7. High Court's judgment and appeal to Supreme Court.
8. Relevant provisions of the Agreements.
9. Misrepresentation and non-supply of documents.
10. Award of the Arbitral Tribunal.
11. Submissions by both parties.
12. Public policy under Section 34 of the Arbitration and Conciliation Act.
13. Application of the law by the Supreme Court.

Detailed Analysis:

1. Invitation for Refurbishment Proposals and Issuance of Provisional Letter of Intent:
M.P. Power Generation Co. Ltd. (the Board) invited proposals for refurbishment of Units 3 and 4 of the Thermal Power Plants at Amarkantak. A provisional Letter of Intent was issued to Respondent No.1, ANSALDO Energia SPA (the Claimant) on 11th May 1999, followed by four Agreements signed on 24th August 1999.

2. Furnishing of Bank Guarantees and Performance Bond:
The Claimant furnished a Bank Guarantee for ?9,29,20,000/- and another for US $ 1,708,100/- as per the Onshore and Offshore Supply Agreements. Additionally, a Performance Bond for ?18,48,00,000/- was executed by ANZ Grindlays Bank Limited.

3. Determination of Zero Date and Subsequent Correspondence:
The Zero Date was agreed to be 9th March 2000. The Claimant later suspended the performance of the Agreement, citing non-furnishing of a Letter of Comfort from the Power Finance Corporation and misrepresentation of the warranty in Clause 19.2 (vii).

4. Invocation of Bank Guarantees and Issuance of Notice for Default:
The Board invoked the three Bank Guarantees on 23rd June 2001 and issued a notice for default on 29th August 2001, leading to the termination of the contract. The Claimant raised a dispute which was referred to Arbitration.

5. Arbitration and Tribunal's Award:
The Arbitral Tribunal passed an award in favor of the Claimant, declaring the Bank Guarantees wrongfully invoked and the agreements wrongfully terminated. The Tribunal awarded the Claimant sums with interest and costs of arbitration.

6. Section 34 Application and Additional District Judge's Findings:
The Board's petition under Section 34 of the Arbitration and Conciliation Act was allowed by the learned Additional District Judge, setting aside the Arbitral Tribunal's award. The Judge upheld the Tribunal's findings on several issues but found fault with the award related to Bank Guarantees and amounts specified in Exhibit-GG.

7. High Court's Judgment and Appeal to Supreme Court:
The High Court set aside the judgment of the Additional District Judge and restored the Arbitral Tribunal's award. The High Court held that the Additional District Judge erred in interfering with the Tribunal's findings on Issues 9 to 12.

8. Relevant Provisions of the Agreements:
The Agreements included provisions for Performance Guarantees, issuance of Bank Guarantees against advance payment, and termination clauses. The Tribunal found that the Board's termination of the contract was illegal and a breach of fundamental conditions.

9. Misrepresentation and Non-Supply of Documents:
The Tribunal concluded that the Board misrepresented the capacity and operating parameters of the Units and failed to supply relevant records, which was a substantial breach of the contract.

10. Award of the Arbitral Tribunal:
The Tribunal awarded the Claimant amounts for the wrongful invocation of Bank Guarantees and other expenditures. The Tribunal rejected the claim for damages for wrongful termination of the contract.

11. Submissions by Both Parties:
The Board argued that the award was perverse and vitiated by patent illegality, while the Claimant contended that the award was well-reasoned and did not suffer from any infirmity. The Board also argued that the Claimant waived the production of the Letter of Comfort, which the Tribunal rejected.

12. Public Policy under Section 34 of the Arbitration and Conciliation Act:
The Supreme Court referred to the settled law on the scope of Section 34, noting that an award can be set aside if it is contrary to the fundamental policy of Indian law, the interest of India, or justice or morality. The Court emphasized the importance of a judicial approach and the application of mind by the arbitral authority.

13. Application of the Law by the Supreme Court:
The Supreme Court upheld the Tribunal's findings on misrepresentation and non-supply of documents. The Court modified the award by excluding the amounts involved in the Bank Guarantees dated 22.02.2000 and 23.02.2000, as they were for the amounts advanced by the Board. The Court affirmed the award for the amounts related to the Performance Bank Guarantee and the claim in Exhibit-GG.

Conclusion:
The Supreme Court upheld the award of the Arbitral Tribunal with the modification that the Claimant is not entitled to the amounts involved in the Bank Guarantees dated 22.02.2000 and 23.02.2000. The award of ?11,14,55,042/- with interest and ?18,48,00,000/- with interest was affirmed. The appeals were dismissed with the above modification.

 

 

 

 

Quick Updates:Latest Updates