Tax Management India. Com
Law and Practice  :  Digital eBook
Research is most exciting & rewarding
  TMI - Tax Management India. Com
Follow us:
  Facebook   Twitter   Linkedin   Telegram

Home Case Index All Cases Insolvency and Bankruptcy Insolvency and Bankruptcy + Tri Insolvency and Bankruptcy - 2020 (7) TMI Tri This

  • Login
  • Summary

Forgot password       New User/ Regiser

⇒ Register to get Live Demo



 

2020 (7) TMI 235 - Tri - Insolvency and Bankruptcy


Issues Involved:
1. Existence of operational debt and default.
2. Limitation period for filing the insolvency petition.
3. Pre-existing disputes between the parties.
4. Completion of contractual obligations by the Operational Creditor.
5. Calculation of amounts due including taxes and interest.

Detailed Analysis:

1. Existence of Operational Debt and Default:
The Operational Creditor, M/s. Enexio Power Cooling Solutions India Private Limited, alleged that the Corporate Debtor, M/s. MSR Mega Bio Power Limited, defaulted on payments amounting to ?35,02,500/- along with interest @ 24% p.a., totaling ?88,36,537/-. The contract dated 18-12-2010 was for the design, engineering, manufacturing, procuring, testing, and supplying of an Air Cooled Condenser for a power project. Despite repeated reminders and a demand notice issued on 29-3-2018, the Corporate Debtor failed to make the payment.

2. Limitation Period for Filing the Insolvency Petition:
The Corporate Debtor contended that the claim is time-barred as the invoices were raised in 2012, with the last invoice dated 20-7-2012. The Operational Creditor's demand notice was issued on 29-3-2018, beyond the three-year limitation period as per Article 137 of the Limitation Act. The Tribunal agreed, stating that the application should have been filed within three years from the date of the last invoice or the last payment made on 16-6-2012. The Tribunal found the application barred by limitation.

3. Pre-existing Disputes Between the Parties:
The Corporate Debtor argued that there was a pre-existing dispute regarding the completion of the contractual work. A letter dated 3-6-2014 from the Corporate Debtor requested the Operational Creditor to complete the pending works before making further payments. The Tribunal noted that this letter indicated an ongoing dispute about the completion of the work, which constituted a pre-existing dispute.

4. Completion of Contractual Obligations by the Operational Creditor:
The Operational Creditor claimed to have completed the supply and erection work by 29-7-2012. However, the Corporate Debtor's letter dated 3-6-2014 suggested that the work was incomplete. The Tribunal found that the Operational Creditor did not refute the contents of the letter, indicating that the work was indeed pending. This supported the existence of a pre-existing dispute.

5. Calculation of Amounts Due Including Taxes and Interest:
The Operational Creditor argued that the total amount due, including taxes and interest, was ?88,36,537/-. The Corporate Debtor countered that it had paid ?3,76,60,000/-, which was in excess of the contracted price of ?3,75,00,000/-. The Tribunal noted that the Operational Creditor failed to provide evidence that the debt was still appearing in the Corporate Debtor's books of account. Additionally, the Tribunal found no material to support the claim that the Corporate Debtor owed taxes as per the contract.

Conclusion:
The Tribunal concluded that the application was barred by limitation and that there was a pre-existing dispute regarding the completion of the work. The Operational Creditor failed to provide sufficient evidence to support its claims. Consequently, the application for initiating the Corporate Insolvency Resolution Process was rejected.

 

 

 

 

Quick Updates:Latest Updates