Tax Management India. Com
Law and Practice  :  Digital eBook
Research is most exciting & rewarding
  TMI - Tax Management India. Com
Follow us:
  Facebook   Twitter   Linkedin   Telegram

Home Case Index All Cases Indian Laws Indian Laws + SC Indian Laws - 2021 (5) TMI SC This

  • Login
  • Cases Cited
  • Summary

Forgot password       New User/ Regiser

⇒ Register to get Live Demo



 

2021 (5) TMI 623 - SC - Indian Laws


Issues Involved:
1. Refund of the rebate agreed upon by the parties.
2. Grant of escalation of charges for work done beyond the scheduled period.
3. Costs imposed on the appellant by all three forums below.

Issue-wise Detailed Analysis:

1. Refund of the rebate agreed upon by the parties:
The Arbitrator held that the rebate of 16% on the price of construction of 100 units of A and B type quarters was conditional upon the respondent being able to execute both works simultaneously. The Arbitrator based this interpretation on documents, particularly a letter dated 14.06.1988, the award of both contracts on the same date, and the works programme (L2) indicating simultaneous execution. The appellant's failure to deny the L2 programme supported this interpretation. The Arbitrator concluded that the appellant's delay in handing over the sites breached the condition for the rebate, entitling the respondent to a refund. The Court agreed that the Arbitrator's interpretation was reasonable and upheld the award, emphasizing that it does not sit in appeal over an arbitrator's decision as long as a possible view is taken.

2. Grant of escalation of charges for work done beyond the scheduled period:
The Arbitrator awarded escalation charges for work done beyond the contract period, attributing the delay to the appellant. In Civil Appeal No. 6483 of 2014, the Arbitrator awarded ?17,86,212 against a claim of ?66,98,773, and in Civil Appeal No. 6484 of 2014, ?3,03,419 against a claim of ?42,20,261. The Arbitrator interpreted the firm price clause as applicable only during the original contract period, not beyond. The Arbitrator's decision was based on the appellant's acceptance of work beyond the contract period without objections. The Court upheld this interpretation, referencing similar judgments (e.g., Assam State Electricity Board v. Buildworth Private Limited) and distinguishing the present case from others cited by the appellant, such as New India Civil Erectors (P) Ltd. v. ONGC, where specific contract clauses excluded price escalation.

3. Costs imposed on the appellant by all three forums below:
The appellant contested the costs imposed by the forums below. However, the counsel for the appellant did not press this issue, and considering the quantum involved, the Court was not inclined to interfere with the costs imposed.

Conclusion:
The Supreme Court found no reason to interfere with the High Court's judgment. The Civil Appeals filed by the appellant were dismissed, and the appellant was directed to pay the pending amounts to the respondent within six months from the date of the judgment. Pending applications were also disposed of.

 

 

 

 

Quick Updates:Latest Updates