Article Section | |||||||||||
ON GOING REAL ESTATE PROJECT WILL COME UNDER ‘RERA’ |
|||||||||||
|
|||||||||||
ON GOING REAL ESTATE PROJECT WILL COME UNDER ‘RERA’ |
|||||||||||
|
|||||||||||
The proviso to Section 3 of the Tamil Nadu Real Estate (Regulation and Development) Act, 2016 provides that the projects that are ongoing on the date of commencement of this Act and for which the completion certificate has not been issued, the promoter shall make an application to the Authority for registration of the said project within a period of three months from the date of commencement of this Act. The Tamil Nadu RERA Authority upheld the validity of the proviso to section 3 of the Tamil Nadu Real Estate (Regulation and Development) Act, 2016, in ‘SERENE ROSE RESIDENTS WELFARE ASSOCIATION VERSUS M/S. SERENE SENIOR LIVING (P) LTD. AND COLUMBIA PACIFIC COMMUNITIES PVT. LTD.[ 2021 (3) TMI 976 - TAMIL NADU REAL ESTATE REGULATORY AUTHORITY]. The complaint is filed by senior citizens who formed Serene Rose Residents Welfare Association at Coimbatore. The first respondent undertook the project ‘Serene Rose’ in 2013 with a promised delivery of March 2016. The said deadline was revised to June 2016 for completion of project including all infrastructure facilities. During October 2017 the first occupant owners were allowed to occupy without common facilities such as electricity supply etc. The power supply was given in February, 2018. The service lift was commissioned on 29.03.2019. The completion certificate has not been obtained. In between the provisions of RERA came into effect during 2016. The first respondent did not register with the Authority of RERA. The complaint alleged the following-
The Association filed the present complaint to the Authority seeking the following reliefs-
The first respondent submitted the following before the Authority-
The complainant refused the submissions put forth by the first respondent. The buyers have never agreed to the proposal of building in four phases at any point of time and promised completion by March 2016, within three years from the date of inception. This project must be considered as a single integrated project and should come under RERA’s ambit and audit. The complainant further submitted that assurances were given by the service provider that all works connected with block ‘A’ and ‘C’ and infrastructure will be completed by the end of July 2017. Despite various complaints by the complainant association no remedy has been made out to the complainant association members. The complainant further submitted that the ownership of common facilities should be with the ‘Resident’s Welfare Association’. It was built by money paid by owners while buying their property. In the rejoinder the complaint association prayed for the following-
The second respondent submitted the following before the Authority-
The complainant, in response to the submissions by the second respondent, submitted that the TNRERA came into force in July 2017 and the project was not completed by that time and hence comes under the purview of TNRERA under ‘Ongoing Project’. As per RERA Rules the ‘service provider’ should have been selected by the Residents Association after the promoter hands over the common facilities to the Registered Association. Once TNRERA comes into existence in July 2017 it is the responsibility of the promoter and service provider to abide the rules of TNRERA. In the written submissions, the first respondent stated that the construction of compound wall could not be completed due to outbreak of COVID 19 pandemic and the same would be completed by the end of 2020. The Authority has examined the complaint, counter affidavits of the respondents the rejoinder filed by the complainant. The Authority was to decide whether this project is ‘ongoing project’ or not. The Authority observed that the first respondent did not produce documentary evidence to the effect that the project has been completed on or before 01.05.2017. To qualify as a completed project the real estate projects including common areas and common facilities should be completed in all respects in a habitable condition as on 01.05.2017 to qualify as a completed project. The Authority held that Block ‘A & C’ including common amenities and facilities promised to the allottees in the construction agreement by the first respondent is ‘ongoing project’ only under first proviso to section 3(1) of the Act. The Authority directed the first respondent to register with RERA on or before 15.02.2021. The Authority further directed that the first respondent is obliged to hand over the common areas, the common amenities and facilities to the Association of Allottees as per Section 17 of the Act on or before 28.02.2021. The Authority further directed that the promoter should ensure that all common amenities and facilities as promised in the construction agreement with the allottees are completed in all respects before 31.12.2020. The Authority further observed that the first respondent has sold 25746 sq. ft. to the second respondent. This action is not only in contravention of Section 17 of RERA Act but also against the provision of construction agreement in para 22, 23 and 24 specifying the eligible person to whom the undivided share in the project can be sold. The Authority held that the ownership of the Club house as well as the undivided share of the land on which the superstructure of the Club House is located has to be vested with the Association Allottees only. The same should be conveyed in favor of the complainant association on or before 28.02.2021.
By: Mr. M. GOVINDARAJAN - March 27, 2021
|
|||||||||||
|
|||||||||||