TMI Blog2018 (6) TMI 559X X X X Extracts X X X X X X X X Extracts X X X X ..... ly of pipes at the location specified by the Rajkot Municipal Corporation and the work of underground laying of pipes had already been completed before the appointed date and the work of testing and commissioning of network of pipeline was pending - Only the work of Testing and Commissioning of network of pipeline was pending on the appointed date, for which no input in stock was required to be used on or after the appointed date. Therefore, the condition prescribed at clause (i) of sub-section (6) of Section 140 ibid is not fulfilled. Testing and Commissioning of network of pipeline being part of the contract, Goods and Service Tax is leviable, however, since no input / material is required for such Testing and Commissioning of network of pipeline, transitional Input Tax Credit is not allowable - Applicant is not entitled to avail input tax credit under Section 140(6) of the CGST Act, 2017 and the GGST Act, 2017. Ruling:- The work of laying of underground pipeline network falls under the definition of “works contract” provided under Section 2(119) under the CGST Act, 2017 and the GGST Act, 2017. In respect of that part of supply wherein time of supply is on or after the appoint ..... X X X X Extracts X X X X X X X X Extracts X X X X ..... id Central Excise and VAT. Thereafter the applicant had undertaken excavation work whereby trenches are dug in order to lay the pipes. Once the desired level of depth of soil is dug, the work of laying of pipes started. A network of pipes is made by joining the pipes (either by lamination or welding) so that a permanent structure of pipeline network is formed. The inter-connection of the pipes is designed in such a way that the sewage / liquid / water passes through the network without any leakages. Out of the said network of pipes, the pipes can never be dismantled/ removed as such and in order to dismantle it, the entire pipe network has to be demolished and there is hardly any salvage. After the work of laying is over, the trenches are refilled (covered) and the pipeline network remains underground, invisible to the naked eye. Thereafter the work of testing of network takes place in order to check about leakages and achievement of desired flow of liquid / sewage / water (as the case may be). 4. The applicant submitted that while the project of RMC was unfinished, the Goods and Services Tax Act (GST) got implemented, posing a challenge to the applicant to enjoy the credit of m ..... X X X X Extracts X X X X X X X X Extracts X X X X ..... ove, if at all the pending milestone is considered as a supply exigible to tax, it must be declared as a works contract because in pith and substance, the activity is nothing more but continuation of the creation of the immovable property i.e. network of pipelines. They referred to the definition of works contract as provided under Section 2(119) of the CGST Act, 2017 and the GGST Act, 2017 and submitted that the nature of the work executed by them safely leads one to the conclusion that an immovable property is constructed, ipso facto. 8. With respect to second query about the admissibility of the claim of input credit under transition provisions, they referred to Section 140(6) of the CGST Act, 2017 and GGST Act, 2017 and submitted that they are in possession of the duty paid document and the element of Central Excise and VAT can be identified clearly. The recitals of the contract of RMC ensure that a sizeable cost of materials is not released to the applicant lest the project is abandoned half-way. It is submitted that the project being in a semi-finished stage, though physically, pipes are not visible as they are underground, entitles them to make a valid claim of credit o ..... X X X X Extracts X X X X X X X X Extracts X X X X ..... rder to dismantle it, the entire pipe network has to be demolished and there is hardly any salvage. 11.4 We observe that the underground pipeline network created by joining the pipes either by lamination or welding cannot be dismantled without substantial damage and thus cannot be reassembled, therefore the pipeline network so created would be considered as immovable. As the applicant is engaged in the activity of construction of pipeline network which becomes immovable property wherein transfer of property in goods is involved, the said activity falls within the definition of works contract under the CGST Act, 2017 and the GGST Act, 2017. 12.1 As per clause 6(a) of the Second Schedule read with Section 7 of the CGST Act, 2017 and the GGST Act, 2017, the composite supply, namely works contract as defined in clause (119) of section 2 shall be treated as a supply of services. 12.2 The provisions related to determination of time of supply of services are contained in Section 13 of the CGST Act, 2017 and the GGST Act, 2017. As per sub-section 2 of Section 13 ibid, the time of supply of services shall be the earliest of the following dates namely :- (a) the date of issue ..... X X X X Extracts X X X X X X X X Extracts X X X X ..... nished goods held in stock on the appointed day subject to the following conditions, namely :- (i) such inputs or goods are used or intended to be used for making taxable supplies under this Act; (ii) the said registered person is not paying tax under section 10; (iii) the said registered person is eligible for input tax credit on such inputs under this Act; (iv) the said registered person is in possession of invoice or other prescribed documents evidencing payment of duty under the existing law in respect of inputs; and (v) such invoices or other prescribed documents were issued not earlier than twelve months immediately preceding the appointed day. 13.2 We are informed that the work of supply of pipes at the location specified by the Rajkot Municipal Corporation and the work of underground laying of pipes had already been completed before the appointed date and the work of testing and commissioning of network of pipeline was pending. As submitted by the applicant, only the work of Testing and Commissioning of network of pipeline was pending on the appointed date, for which no input in stock was required to be used on or after the appointed date ..... X X X X Extracts X X X X X X X X Extracts X X X X
|