Tax Management India. Com
Law and Practice  :  Digital eBook
Research is most exciting & rewarding
  TMI - Tax Management India. Com
Follow us:
  Facebook   Twitter   Linkedin   Telegram

Home Case Index All Cases Indian Laws Indian Laws + SC Indian Laws - 2022 (11) TMI SC This

  • Login
  • Cases Cited
  • Referred In
  • Summary

Forgot password       New User/ Regiser

⇒ Register to get Live Demo



 

2022 (11) TMI 1395 - SC - Indian Laws


Issues Involved:
1. Whether the PPA in question is a statutory contract.
2. Scope of judicial review in contractual matters involving the State.
3. Concept of public law in judicial review of contractual matters.
4. Existence of an arbitration clause.
5. Effect of the High Court's judgment in the earlier round of litigation.
6. Impact of disputed questions of facts on the writ petition.
7. Comparison with the Renew Energy case.
8. Effect of non-compliance with Article 9.1 of the PPA.
9. Concept of overwhelming public interest in judicial review of contractual matters.
10. Whether the Supreme Court should interfere with the High Court's judgment.

Detailed Analysis:

1. Whether the PPA in question is a statutory contract:
The Supreme Court analyzed whether the Power Purchase Agreement (PPA) between the parties was a statutory contract. It concluded that the PPA was not a statutory contract. The Court noted that the PPA was entered into by a government-owned company, but it was not made under the executive power of the State within the meaning of Article 298 of the Constitution. The terms and conditions of the PPA were not mandated by any statute but were based on mutual agreement between the parties.

2. Scope of judicial review in contractual matters involving the State:
The Court examined the evolution of judicial review in contractual matters involving the State. It acknowledged that while traditionally, contractual disputes were considered to be outside the scope of writ jurisdiction, the law has evolved to allow judicial review in cases where the State's action is arbitrary, unreasonable, or unfair. The Court emphasized that the State must act fairly and justly in all its actions, including contractual matters, and such actions are subject to judicial review under Article 14 of the Constitution.

3. Concept of public law in judicial review of contractual matters:
The Court reiterated that the State cannot act arbitrarily in contractual matters and must adhere to the principles of fairness and reasonableness. It highlighted that even in the realm of contracts, the State's actions must be informed by reason and must not be arbitrary. The Court cited various judgments to support the principle that the State's actions in contractual matters are subject to judicial review to ensure they comply with the constitutional mandate of non-arbitrariness.

4. Existence of an arbitration clause:
The Court examined the dispute resolution clauses in the PPA and concluded that the PPA did not contain an arbitration clause that would cover the disputes in question. Therefore, the situation contemplated in the earlier judgment in State of U.P. v. Bridge & Roof Co. (India) Ltd., which involved an arbitration clause, did not apply in this case.

5. Effect of the High Court's judgment in the earlier round of litigation:
The Supreme Court analyzed the impact of the High Court's judgment in the earlier round of litigation, which had set aside the initial termination notice issued by the appellant. The Court concluded that the High Court's judgment had effectively decided the issue of non-fulfillment of conditions subsequent, and the appellant could not reopen this issue. The liberty granted by the High Court to pass fresh orders was limited to the aspect of commissioning the project and did not extend to revisiting the issue of conditions subsequent.

6. Impact of disputed questions of facts on the writ petition:
The Court acknowledged that the case involved disputed questions of facts, particularly regarding the readiness of the project for commissioning. However, it emphasized that the existence of disputed facts does not automatically preclude the exercise of writ jurisdiction. The Court held that the writ petition could be entertained if the disputed questions of fact could be resolved based on documentary evidence without the need for a detailed examination of witnesses.

7. Comparison with the Renew Energy case:
The Court compared the case of the first respondent with that of Renew Energy, where the High Court had set aside a similar termination notice. It noted that the High Court had found that the delay in achieving the first milestone was condoned in the case of Renew Energy, and the first respondent's case was similar. The Court concluded that the High Court's judgment in the earlier round of litigation had effectively settled the issue of conditions subsequent, and the appellant could not revisit this issue.

8. Effect of non-compliance with Article 9.1 of the PPA:
The Court examined Article 9.1 of the PPA, which required the appellant to issue a default notice and provide a three-month period for the respondent to rectify the default before terminating the agreement. The Court found that the appellant had not complied with this requirement and had instead issued a termination notice without giving the respondent an opportunity to remedy the default. The Court held that this non-compliance rendered the termination notice invalid.

9. Concept of overwhelming public interest in judicial review of contractual matters:
The Court addressed the appellant's argument that public interest lay in not purchasing power at a higher rate from the respondent. It emphasized that public interest cannot be determined solely based on monetary considerations. The Court noted that the rates in the PPA were determined through a competitive bidding process, and the respondent's bid was the lowest. It concluded that the appellant's attempt to secure a reduction in the rate did not justify the arbitrary termination of the contract.

10. Whether the Supreme Court should interfere with the High Court's judgment:
The Supreme Court concluded that the High Court's judgment did not warrant interference. It upheld the High Court's decision to set aside the termination notice and directed the appellant to comply with the contractual obligations. The Court emphasized that the appellant's actions were arbitrary and did not comply with the requirements of the PPA. The appeals were dismissed, and the parties were directed to bear their own costs.

 

 

 

 

Quick Updates:Latest Updates