Tax Management India. Com
Law and Practice  :  Digital eBook
Research is most exciting & rewarding
  TMI - Tax Management India. Com
Follow us:
  Facebook   Twitter   Linkedin   Telegram

Home Case Index All Cases Companies Law Companies Law + SC Companies Law - 2006 (5) TMI SC This

  • Login
  • Cases Cited
  • Referred In
  • Summary

Forgot password       New User/ Regiser

⇒ Register to get Live Demo



 

2006 (5) TMI 442 - SC - Companies Law


Issues Involved:
1. Jurisdiction of the Arbitrator
2. Validity of Partial Award
3. Delay and Disruption Claims
4. Uninvoiced Claims
5. Method for Computation of Damages
6. Clause 37 of the Main Contract
7. Method of Measurement
8. Buoyancy Tanks for ED and EE Jackets
9. Tie-Downs and Sea-Fastening
10. Foreign Exchange Loss
11. Substitution of Materials
12. Interest

Detailed Analysis:

1. Jurisdiction of the Arbitrator:
The arbitrator's jurisdiction was questioned under Section 34 of the Arbitration and Conciliation Act, 1996. The court noted that under the 1996 Act, the party questioning the jurisdiction must raise the issue before the arbitrator. This was not done by BSCL, and thus, the arbitrator's jurisdiction was upheld.

2. Validity of Partial Award:
The 1996 Act does not explicitly mention "partial awards," but includes "interim awards" under Section 2(c). The court found that the partial award issued by the arbitrator was final in all respects concerning the disputes referred to him and was thus valid. BSCL did not raise any objections regarding the arbitrator's jurisdiction during the proceedings, and the partial award was treated as a final award subject to challenge under Section 34.

3. Delay and Disruption Claims:
The arbitrator found that delays caused by BSCL entitled MII to compensation for increased overhead, decreased profit, and additional project management costs. The Emden Formula was applied to quantify these damages. The court upheld the arbitrator's decision, noting that the second part of Section 55 of the Indian Contract Act applied, allowing for compensation even if time was not of the essence of the contract.

4. Uninvoiced Claims:
The arbitrator initially rejected uninvoiced claims but later awarded MII compensation for structural material procurement, additional barge trips, and pipeline surveys based on evidence and correspondence. The court upheld this, stating that claims could be made through correspondence or meetings and did not necessarily require invoices.

5. Method for Computation of Damages:
The arbitrator used the Emden Formula to compute damages for increased overhead and loss of profit. The court found this method acceptable and widely recognized in construction contracts. The application of this formula was within the arbitrator's discretion and did not violate Indian law.

6. Clause 37 of the Main Contract:
Clause 37 excluded liability for consequential damages. The court found that MII's claims were for direct losses due to BSCL's breach of contract, not consequential damages. Therefore, Clause 37 did not apply to MII's claims.

7. Method of Measurement:
The arbitrator adopted the AISC Code for calculating the "as fabricated tonnage," which was accepted by both parties during the arbitration. The court upheld this method, noting that the contract did not specify a method of measurement, and the AISC Code was an industry standard.

8. Buoyancy Tanks for ED and EE Jackets:
The arbitrator found that substantial fabrication work was done by MII in refurbishing the buoyancy tanks, based on evidence and witness testimony. The court upheld this finding, stating it was a matter of fact and not perverse.

9. Tie-Downs and Sea-Fastening:
The arbitrator awarded MII compensation for fabrication work related to tie-downs and sea-fastening, which required substantial fabrication. The court upheld this, noting that the contract covered these items under the fabrication scope.

10. Foreign Exchange Loss:
The arbitrator awarded MII compensation for foreign exchange losses due to BSCL's breach of contract. However, the court found that the exchange rate clause, which was frozen at Rs. 100 = US$ 8.575, applied to all claims, including those for fabrication and installation. The award was modified to reflect this.

11. Substitution of Materials:
The arbitrator awarded MII compensation for the substitution of heavier materials. The court found that ONGC had not agreed to pay for the substituted materials, and MII had implicitly accepted this. The award was modified to exclude compensation for the increased tonnage due to substitution.

12. Interest:
The arbitrator awarded interest at 10% per annum on the principal amount and future interest at the same rate. The court reduced the interest rate to 7.5% per annum, considering the long lapse of time.

Conclusion:
The award of the arbitrator was upheld in part and modified in specific areas, such as the foreign exchange loss and substitution of materials. The interest rate was reduced to 7.5% per annum. The court emphasized that the arbitrator's findings on facts and the application of industry-standard methods were within his jurisdiction and discretion.

 

 

 

 

Quick Updates:Latest Updates